Oil Venture - Buying (Chevron - Sudan) USA
Accordingly Concorp Int. owns a 24 million acre concession comprising Muglad and Melut Blocks, with proven reserves of 133 billion barrels of oil and recoverable reserves of 280 million barrels of oil
Chevron's Overseas President Richard Matzke and Concorp Int. President M. A. Jarelnabi signed the purchase agreement of Chevron Oil Company of Sudan.
Concorp Khartoum Refinery Sudan
Concorp Khartoum Refinery Storage Capacity is as follows:
- One Tank, with a capacity of 5000m3 to receive crude. A second tank of equal size is to be constructed, the platform for it is ready
- A 2100m3 day tank to supply the refinery with crude from the main tank
- Two tanks each with a capacity of 2100m3 to receive the furnace oil produced by the refinery
- One tank with a capacity of 1050m3 to receive slops
- Six tanks with a capacity of 600m3 each
Refineries
Concorp Khartoum Refinery Sudan
Concorp Khartoum Refinery Sudan
Abujabra Refinery - Sudan
Sidiqi Oil Field Pipeline
Concorp Petrol Station
Development of Sedigui Oil Field, north of Lake Chad and construction of a 341km pipeline
In the year 2000, Concorp signed an EPCM contract (Engineering, Procurement, Construction and Management) with government od Chad for USD 34.0 million to develop the Sedigui Oil Field, north of Lake Chad and build a 341km pipeline to transport crude oil to Concorp Ndjamena refinery that will process Sedigui crude oil for the local and export market.
Concorp developed Sedigui Oil Field which consists of two oil wells.
The job requires:
- Opening of the well
- Drilling water wells for water injection
- Cleaning of the wells
- Installation of x-masstrees
- Erecting network of pipes to transport crude oil to production facilities
- Building of crude tanks and pumpfarm
- Installation of power generating system
On the other hand Concorp laid 341km of 6" pipeline to carry crude oil produced from Sedigui Oil Field north of Lake Chad to Concorp N'djamena refinery.
The job requires:
- Laying of 341km of 6" pipeline
- Welding of pipes using mobile welding machines & lifting equipment
- Pipes coating
- X-Raying the pipeline
- Building of pump stations along the pipeline
Hannan Kuwait Village - Sudan
In keeping with our programme of expansion Concorp opened its office in Sudan in 1982 and started two contracts. The Hannan Village Project consisting of schools, shops, dormitories, housing and mosque in the south-east of Sudan at a first phase cost of US$ 5.15 million
Phase 2 took this figure to US$ 10 million with the addition of roads, main drainage, water purification, landscape and agricultural farms.
The donating clients are the Women's Culture, Social Society of Kuwait and Usrati Magazine. On their behalf the contract was signed by Sheikh Mohammed Naser Al Hamdam, the Dty. Minister of Awqaf and Islamic affairs - Kuwait and Sheikh Yousif Jasim Al Hijji, former minister of Awqaf and Islamic affairs - Kuwait and on behalf of the contractor Mr. M. A. Jarelnabi Abbas, Chairman & Managing Director of Concorp International Limited.
Greenland Towers - Uganda
King Fahd Plaza - Uganda
Shari River Bridge - Tchad